How to compare interior quotations accurately
Compare interior contractor quotations using the same bill of quantities, specifications, exclusions and delivery assumptions.
By Sree Balaji Interiors · Interior project planning
How do you compare interior quotations fairly?
Compare quotations only when they are based on the same brief, drawings, bill of quantities (BOQ) and specifications. Then compare them line by line: quantities, materials, brands, what is excluded, provisional sums, payment terms and how changes are priced. The lowest total is not the cheapest quotation if it leaves out work you will pay for later.
Use the same scope for everyone
Give every contractor the same brief, drawings and schedule of work, and ask them to price the same BOQ, or to show their own quantities against your drawings. If one contractor quotes from a site visit and another from a WhatsApp photo, the numbers will not be comparable.
Check that each quotation includes:
- procurement, transport and loading, unloading and shifting,
- site protection, debris removal and final cleaning,
- supervision and site management,
- GST, stated clearly as included or extra.
Compare specifications, not only prices
Two quotations for "false ceiling" can mean very different things. Compare:
- material and brand (e.g. gypsum board make, laminate or veneer brand and thickness, tile size and grade),
- hardware make for drawers and hinges,
- electrical cable and switch makes,
- paint system and number of coats.
Where a quotation says "equivalent" or "as per approval", ask what it priced.
Identify exclusions and assumptions
Ask each contractor to list what is not included. Common exclusions are air-conditioning equipment, fire safety works, loose furniture, IT and AV cabling, statutory approvals, building management deposits and electricity and water during work. Ask which quantities are provisional, meaning they will be measured later, and which items depend on a site survey or opening up existing work.
Check payment terms and programme
Compare the payment schedule: advance, stage payments and retention. Payments should be linked to progress you can see. Compare the programme each contractor offers, and what it assumes about approvals, site access and your decisions. A quotation with an unrealistically short programme is a warning sign.
Agree how changes will be priced
Changes happen on almost every project. Ask how variations will be priced (rates from the quotation, or new rates) and approved (a written change note before work). Agree this before work starts. The goal is a quotation you can understand and manage through the project, not just the lowest first number.
A simple comparison method
- Put every quotation into one spreadsheet, using the same line items.
- Mark items missing from each quotation and get a price for them.
- Mark specification differences and ask for like-for-like prices.
- Add exclusions you will have to buy separately.
- Compare the adjusted totals, payment terms and programme together.
Checklist: before you choose
- Same brief, drawings and BOQ for all
- Line-by-line comparison done
- Brands and specifications matched
- Exclusions listed and priced
- Provisional items identified
- GST treatment clear
- Payment stages linked to progress
- Variation pricing and approval agreed
- Programme realistic for approvals and lead times